BORMAN EXPRESSWAY - I-80/94 RECONSTRUCTION

PROJECT PURPOSE

The purpose of this project is to widen I-80/94 to 4 lanes wide from Broadway (SR-53) to Central Ave. along with reconstructing the I-65 interchnage.

PROJECT STATS

Basic Information:
Project Priority URGENT
Project Area:
I-80/94 from Broadway to Central Ave
Status Construction Phase 3
Begin Construction 2007
Estimated Project Completion July 2011

PROJECT DETAILS

This project was completed in three phases. Phase 1 included the construction of new ramps from northbound I-65 to westbound I-80/94 and eastbound I-80/94 to southbound I-65, and rehabilitation of three bridges within that area of roadway. Phase 2 upgraded I-65 over I-80/94 and upgraded the other ramps between the Borman Expressway and I-65. Phase 3 is still under construction and is scheduled to be complete in July 2011 and will widen I-80/94 to 4 lanes wide from Broadway (SR-53) to Central Ave, add auxiliary lanes, and replace the pavement in this section.(Source: INDOT)



Back to Top
return to the Project Page

Updated 01/04/2011